  • Question 61:

    Materials

    Your customer want to use scheduling for network to specify planned dates of task. In the SAP project system there are different set of dates that can be scheduled.

    Which set of dates can be used for scheduled for network?

    Note : there are 2 correct answer for this question.

    A. Planned dates

    B. Fundamental dates

    C. Basic dates

    D. Baseline dates

    E. Forecast dates

  • Question 62:

    A customer project must be finished at a given due date. The project consists of WBS elements and networks. What scheduling type do you use?

    A. Only capacity requirements

    B. Forward

    C. Current date

    D. Backward

  • Question 63:

    A component is assigned to a network activity. What are the prerequisites to generate project stock reservations? Note: There are 3 correct answers to this question

    A. The network activity is assigned to a WBS element

    B. The network is assigned to a sales order item

    C. The material master of the component must permit project stock management

    D. The Project Stock indicator is set in the project definition (non-valuated or valuated)

    E. A procurement indicator must be assigned to the activity

  • Question 64:

    Resources

    Which of the following transactions can you use to post actual cost for external processing?

    Note : there are 2 correct answer for this question.

    A. Approval of a service entry sheet

    B. Posting a goods receipt

    C. Creating a service entry sheet

    D. Approval of a good receipt.

    E. Creating a purchase order.

  • Question 65:

    What business transactions can be used with Project-Oriented Procurement (ProMan)? Note: There are 3 correct answers to this question

    A. Confirm production order

    B. Stock transfer posting

    C. Generate purchase requisition

    D. Generate delivery

    E. Cancel goods issue

  • Question 66:

    What could be a reason to use expert mode in the valuation method for results analysis?

    A. Billing WBS elements belonging to different company codes

    B. Assignments of different accounts for postings to financial accounting

    C. Usage of different line ID

    D. Valuation in different currencies

  • Question 67:

    Float time is calculated during scheduling.

    Which of the following statements about float time are correct?

    Note: There are 3 correct answers to this question

    A. Float time can be negative

    B. Activities with the time constraint "Must start on" always have a negative float time

    C. The float time of WBS elements is calculated by extrapolation

    D. By default, critical activities have a float time, which is less than or equal to zero

    E. The maximum size of a free float is as large as the total float of an activity

  • Question 68:

    Which of the following data can be maintained in a standard network? Note: There are 3 correct answers to this question

    A. Document information records

    B. Internally processed activities

    C. Basic dates for activities

    D. Material components

    E. Relationships

  • Question 69:

    You are using network and internal activities in your project . You have already create a purchase requisition and the bid invitation, and have entered the quotation ...

    What is the typical sequence for the following business transactions and document.

    A. Benefic check-Acceptance of performed service-vendor selection-purchase order handing-purchase order monitoring-Good receipt-invoce ..

    B. Vendor selection-purchase order handing-purchase order monitoring-Benefic Check-Acceptance of performed services.

    C. Vendor selection-purchase order handing-invoice receipt-purchase order monitoring-Good receipt.

    D. Vendor selection-Purchase order handing-purchase order monitoring-Good receipt-Invoice receipt.

  • Question 70:

    You have a project with a network, material and milestone. You want to plan an activity to start two days after its predecessor. How can you do that?

    Note : there are 2 correct answers for this question.

    A. Use an offset of two days for the relationship of both activities.

    B. Use an offset of two days for milestone date.

    C. Use an offset of two days for the requirement date of the material component

    D. Calculate the start date of the activity and set the constraint "Must start on" accordingly.

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only SAP exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your C_TS412_2021 exam preparations and SAP certification application, do not hesitate to visit our Vcedump.com to find your solutions here.